Contractors cannot recover in negligence from design professionals for economic losses caused by errors in the drawings and specifications. The ...

Who Is Responsible For Errors In Construction Plans?

The law says that the contractor has an obligation to notify the owner of any defects in the plans—in other words, a builder cannot just look at ...

Whose Design Is It Anyway? Attempts to shift the burden of errors

Just because a design contains errors does not mean that the architect is liable to the owner or contractor for the fix.

Standard of care: Confronting errors & omissions up front

Moreover, design documents are not products, either. Construction document drawings and specifications are simply instruments of the architect's service, which ...

If the architect's design is faulty, but the contractor mistakenly builds ...

Design faults are a liability of the architect or engineer, who frequently have to pay the contractor to fix the issue. Contractors are paid to ...

The Shop Drawing Liability Debate | phcppros

... design professionals can be liable for ... The Contractor shall not be relieved of responsibility for errors or omissions in Shop Drawings ...

Vicarious liabiality and who's responsibailities for errors and ...

Unless the error or omission relates to conformance with the design documents (the Architect should be reviewing all drawings for general ...

Is a contractor obligated to draw attention to errors within an ...

Generally speaking, a contractor has no obligation nor liability for design. However, a court may take a dim view of a contractor entering ...

Who PAYS for the Architect's MISTAKES

If they have complied with the prevailing standard of care, the courts generally will find the designers are not liable for any resulting errors and omissions.

Claim for Design Error - Engineering project management general ...

Contractually, check with a lawyer, but your approach will not likely work. A contractor, unless he's responsible for the design, ...

Dealing with errors and omissions - The Construction Specifier

A design error is an instruction (or lack of instruction) in the plans and specifications that, if followed by the contractor, will require ...

36.609-2 Redesign responsibility for design errors or deficiencies.

(a) Under architect-engineer contracts, contractors shall be ... drawings, specifications, or other items or services furnished contain ...

JBCC – Can a Contractor be held liable for errors in design?

In conclusion, an error in the design does not necessarily absolve the Contractor from liability, and Contractors must note that its common law ...

The New Reality of Design Responsibility, Common Sense ...

The consequences of a contractor taking on design responsibility can be costly because with responsibility generally comes liability. Errors or omissions in ...

CONTRACTOR'S DESIGN LIABILITY ON BUILD-ONLY PROJECTS

... design drawings; does it waive off the responsibility of identifying errors or omissions? Adding more, can the contractor proceed with ...

Assessing Defective Design Liability on Federal Design-Build Projects

Contractors regularly exercise broad discretion with respect to the specifications in design-build contracts, meaning the Spearin doctrine will ...

Design Liability: Claims and Recovery - IRMI

Because the contractor is liable to the owner for delivering a completed project in accordance with the specifications of the DB contract, the ...

Design Defects and Personal Liability: When Can Architects and ...

If a claim for breach of contract is made against an individual responsible for the design errors, the individual can often point to the ...

Liability for Flawed Shop Drawings - Greenberg Traurig, LLP

work as they should, contractors have argued that they are excused from responsibility because the design pro- fessional “approved” the shop ...

Understanding Design Defect Legal Liability

Under the Spearin Doctrine, the contractor should be able to rely on the accuracy and completeness of those drawings in completing the ...